State/Project-wise Central Sector Infrastructure Projects Delayed by More than 12 Months Due to Pending Clearence from Ministry of Environment and Forests in India (As on 01-05-2014) | |||||||
Project | Date of Approval | Original Date of Commi- ssioning (Month/ Year) | Anticipated Date of Commi- ssioning (Month/ Year) | Original Cost (Rs. In Crore) | Antici- pated Cost (Rs. In Crore) | Cost Overrun (%) | Time Overrun (Months) |
Chhattisgarh | |||||||
Coal | |||||||
Kartali (East) OCP (2.50 Mty) | |||||||
Manikpur OC Expansion (3.5 Mty) | |||||||
Kusmunda Expn. Ocp (Secl)(10-15) Mty | |||||||
Jharkhand | |||||||
Coal | |||||||
Purnadih Ocp (3.0 Mty) | |||||||
Tapin OCP (2.5 Mty) | |||||||
Power | |||||||
Transmission System for Phase-1 Generation Projects in Jharkhand and West Bengal-Part-A1 | |||||||
Maharashtra | |||||||
Petroleum | |||||||
Pipeline for Transfer of LPG From BPCR/HPCR to Uran LPG Plant | |||||||
Mizoram | |||||||
Power | |||||||
Tuirial Hydro Electric Project (60MV) | |||||||
Railways | |||||||
Bhairabi Sairong. NL, NEFR | |||||||
Mulit State | |||||||
Petroleum | |||||||
Paradip-Raipur-Ranchi Pipeline | |||||||
Power | |||||||
765 KV Pooling Station and Network with DVC and Maithob RBC | |||||||
Supplimentary Transmission Associated With DVC and Maithon RBC | |||||||
Transmission System of Vindhuachal -IV and Rihand -III Gen. Proj | |||||||
TR. System Associated With Mundra Ultra Mega Power Project | |||||||
Odisha | |||||||
Coal | |||||||
Kaniha OCP, MCL, (10.0 MTY) | |||||||
Hingula OC-II Exp. Ph-III (15 MTY) | |||||||
Ananta OC Expansion Ph-III (15.0 MTY) | |||||||
Sikkim | |||||||
Railways | |||||||
Sevok Rangpo, NEFR | |||||||
Telangana | |||||||
Coal | |||||||
Ramagundam OC-II Extension | |||||||
Manuguru OC-II Extension Phase-II | |||||||
Uttar Pradesh | |||||||
Power | |||||||
Tehri Pumped Storage Plant (1000 MW) |