Category-wise Area Applied and Diverted of Various Projects Pending for Forest Clearance under Forest Clearance (FC) Act, 1980 in Arunachal Pradesh (2013-2014 to 2016-2017-upto 29.11.2016) | |||||
(In HA) | |||||
Proposals | Category | Area Applied | Area Diverted | Submition Date | New Status |
Proposal for Diversion of 10.30 HA. of Forestland for Construction of Keyi Hep (23 MW) in Lower Subansiri State of Arunachal Pradesh by M/s Dd Hydro Power & Developers Pvt. Ltd. | |||||
Proposal for Diversion of 32.898 HA of Forestland for Improvement of Hunlianini Road to Nhdl Specification from 0 Km to 23.82 Km by Brtf under Lower Dibang Valeey State | |||||
Proposal for Diversion of 4.41 HA Forestland for Const/ Improvement of Road Sector from 159.48 (Old) Km/ 158.25 (New) Km to Chung Bridge of Orangkalaktang- Shergaon-Rupa-Tenga by Brtf in West Kameng State | |||||
Proposalfor diversion of 30.67 HA of forestland for Contn./Imp. of Along(Pangin)-Ditte-Dime-Migging- Tuting Road by BRTF in Upper Siang State. | |||||
Proposal for Diversion of 16.07 HA of Forestland for Constn./imp. of Along(Pangin)-Ditte-Dime-Migging- Tuting Road from 75.40 km to 90.40 km by BRTF in Upper Siang State. | |||||
Proposal for Diversion of 29.00 HA of Forestland of Imp/ Widening of Along(Pangin)-Ditte-Dime-Miggingtutinh Road Proposal for Diversion of 29.00 HA of forestland of Imp/ Widening of Along(Pangin)-Ditte-Dime- Miggingtutinh Road From 40.00 Km to 65.00 Km by Brtf at Upper Siang State | |||||
Proposal for Diversion of 20.93 HA of Forestland of Imp/ Widening of Along(Pangin)-Ditte-Dime-Miggingtutinh Road from 90.40 Km to 110.40 Km by Brtf at Upper Siang State | |||||
Proposal for Diversion of 17.626 HA of Forestland of Imp/ Widening of Along(Pangin)-Ditte-Dime-Miggingtutinh Road from 240.40 Km to 256.40 Km by Brtf at Upper Siang State | |||||
Proposal for Diversion of 14.802 HA of Forestland of Imp/ Widening of Along(Pangin)-Ditte-Dime-Miggingtutinh Road from 226.80 Km to 240.40 Km by Brtf at Upper Siang State | |||||
Proposal for Diversion of 22.08 HA of Forestland of Imp/ Widening of Along(Pangin)-Ditte-Dime-Miggingtutinh Road from 161.40 Km to 181.40 Km by Brtf at Upper Siang State | |||||
Proposal for Diversion of 18.37 HA of Forestland of Const. of Tuting Battlion Road from 0.00 Km to 6.975 Km by Brtf at Upper Siang State | |||||
Proposal for Diversion of 41.33 HA Forestland for Construction of Mekaroing-Hunli Road from 47.00 Km to 62.97 Km by Brtf in Dibang Valley State. | |||||
Proposal for Diversion of 156.828 HA of for Estland for Construction of Hunli-Anini Road to NHDI Specification from 23.82 Km to 138.00 Km in Dibang Valley State of A.P. | |||||
Proposal for Diversion of 180.828 HA for Construction of Changlangkhimyang-Sangkhawa-Hawai-Lazuwakka Road (88.00 to 161.00 Km) by Brtf at Arunachal Pradesh | |||||
Proposal for Diversion of 29.862 Ha forestland for Imp. of Tato-Mechuka Road from 0.00 Km to 46.30 Km by Brtf in West Siang State of Ar.Pr. | |||||
Proposal for Diversion of 18.63 HA of Forestland for Cons- truction of Pareng Hep (14.5 MW) in Papumpare State of Arunachal Pradesh by Virtuaal Pareng Hydro Pvt. Ltd | |||||
Proposal for Diversion of 439.68 HA of Forestland for Construction of Hirong Hydro Electric Project (500 MW) in West Siang Dist. of Arunachal Pradesh by M/s Jaypee Arunachal Power Ltd. | |||||
Proposal for Diversion of 3.6747 HA of Forestland for Construction of 132 KV Lilo of 132 Kv S/C Nirjuli-Dikrong Transmission Line at Papumpare by Neepco | |||||
Proposal for Diversion of 29.76 HA of Forestland for Construction of Anonpani Hydro Electric Project (22 MW) by M/s Etalin Hydro Electric Power Company Ltd at Dibang Valley. | |||||
Proposal for Diversion of 5.30 HA of Forestland for Construction of Kaying Hydro Electric Project (14 MW) in West Siang State of Arunachal Pradesh by M/s Sarda Eco Power Ltd | |||||
Proposal for Diversion of 4.8735 HA of Forestland for Construction and Shifting of Tower Location for 57 to 64 of 132 Kv S/C Nirjuli-Dikrong Transmission Line of Power Grid Corporation of india Ltd. (Falling under Submergence Area of Pare-Hep) in Connection with Lilo to Be Linked with Pare- Hep for Evacuation of Power-by Neepco Ltd. | |||||
Proposal for Diversion of 6.4314 HA of Forestland for Construction of 132 KV D/C Lilo Overhead Transmission Line Link with The 132 Kv D/C Hoj-Itanagar Transmission Line for Evacuation of Power From 132 Kv Switchyard of Pare Hep- by Neepco Ltd. | |||||
Proposal for Diversion of 22.35 HA (8.85 Ha in Eaglenest Wls & 13.50 HA in Sessa Orchid Sanctuary) of Forestland for Improvement/Widening of Baliparacharduar-Tawang Road 50.00 Km to 88.00 Km in West Kameng State of Arunachal Pradesh by BRTF | |||||
Proposal for Diversion of 22.35 HA (8.85 Ha in Eaglenest WLS & 13.50 HA in Sessa Orchid Sanctuary) of Forestland for Improvement/Widening of Baliparacharduar-Tawang Road 50.00 Km to 88.00 Km in West Kameng State of Arunachal Pradesh by Brtf | |||||
Revised Proposal for Diversion of 1165.66 HA includind (91.33 HA under Ground Area) of Forestland for Construction of Etalin Hydro Electric Project (3097 Mw) in Dibang Valley State of Arunchal Pradesh by M/s Etalin Hydro Electric Power Company Ltd | |||||
Proposal for Diversion of 153.77 Ha= (36.07HA+117.70 HA) of Forestland for Laying of 132 Kv S/C Transmission Line from Pasighat to Roing in East Siang and Dibang Valley State of Arunachal Pradesh by M/s Power Grid Corporation of india Ltd. | |||||
Proposal for Diversion of 153.77HA=(36.07HA+117.70HA) of Forestland for Laying of 132 Kv S/C Transmission Line from Pasighat to Roing in East Siang and Dibang Valley State of Arunachal Pradesh by M/s Power Grid Corporation of india Ltd. | |||||
Proposal for Diversion of 108.937 Ha (2.16 HA +106.777 HA) of Forest Land for Laying of 132 Kv/S/C Transmission Line from Roing to Tezu in Lower Dibang Valley andLohit States of Arunachal Pradesh by M/s Power Grid Corporatopn of India | |||||
Diversion of 2600.00 HA of Forestland for Baliliang Field Firing Range with Impact Zone of 5.00 HA in Favour of Indian Army in Lohit State of Arunachal Pradesh | |||||
Proposal for Diversion of 4.50 HA of Forestland for Impro- vement of Akajan-Likabali-Bame Road From 65.00 Km to 71.00 Km by Brtf in West Siang State of Arunachal Pradesh | |||||
Diversion of 36.27 HA of Forestland for Construction/ Improvement of Wakkakanu Road From 0.00 Km to 20.50 Km by Brtf in Longding State of Arunachal Pradesh | |||||
Revised Proposal for Diversion of 16.37Ha of Forestland for Construction of Road From Sisseri Bridge to Sinekorong Bridge On Silluk-Dambuk Road of Trans Arunachal Highway Under Pm`S Package by Brtf in Lower Dibang Valley State of Arunachal Pradesh | |||||
Diversion of 57.00 HA of Forestland for Construction of Tato-Taliha (Tato End) Road From 30.00 Km to 51.76 Km by Brtf in West Siang State of Arunachal Pradesh. | |||||
Proposal for Diversion of 160.958HA (60.588 HA+ 100.37HA) of Forestland for Laying of 132 Kv S/C Transmission Line from Tezu to Namsai in Lohit States of Arunachal Pradesh by M/s Power Grid Corporation of india Ltd. | |||||
Proposal for Diversion of 160.958 HA (60.588 Ha+ 100.37HA) of Forestland for Laying of 132 Kv S/C Transmission Line from Tezu to Namsai in Lohit States of Arunachal Pradesh by M/s Power Grid Corporation of india Ltd. |