Central Sector Infrastructure Projects Delayed by More than 12 Months Due to Pending Clearence from Ministry of Environment and Forests in Chhattisgarh (As on 01.05.2014) | |||||||
Project | Date of Approval | Original Date of Commi- ssioning (Month/ Year) | Anticipated Date of Commi- ssioning (Month/ Year) | Original Cost (Rs. In Crore) | Antici- pated Cost (Rs. In Crore) | Cost Overrun (%) | Time Overrun (Months) |
Chhattisgarh | |||||||
Coal | |||||||
Kartali (East) OCP (2.50 Mty) | |||||||
Manikpur OC Expansion (3.5 Mty) | |||||||
Kusmunda Expn. Ocp (Secl) (10-15) Mty | |||||||
India |