Project-wise Financial and Physical Progress of Basic Service to Urban Poor (BSUP) under Jawaharlal Nehru National Urban Renewal Mission (JNNURM) in West Bengal (As on 26.11.2014) | ||||||||
Projects | Cities Approved Date | No. of Project | Financial Progress (Rs. in Crore) | Physical Progress | ||||
Project Cost Approved | Central Share Committed | Central Share Released | No. of DU`s Approved | No. of DUs In Progress | No. of DUs Completed | |||
BSUP Scheme for Durgapur. Distt. Bardhaman. Asansol Urban Region. West Bengal | ||||||||
BSUP Scheme for the Town of Kulti Asansol (West Bengal) | ||||||||
Bsup Scheme For Thr Town of Jamuria Municipality (Phase.I). Asansol. West Bengal | ||||||||
BSUP Scheme for the Town Raniganj Municipality (Phase.I). Asansol. West Bengal | ||||||||
BSUP Scheme for Jamuria (Phase II) under JnNURM, West Bengal | ||||||||
BSUP Scheme for the town of Raniganj (Phase-II) under Asansol region, West Bengal. | ||||||||
1371 DUs Low Cost Housing For Urban Poor Under BSUP Component Asansol, West Bengal | ||||||||
912 Relocation DUs BSUP Scheme for the Town of Durgapur (Phase-IV), Burdwan. West Bengal. | ||||||||
1937 DU`s BSUP Scheme for the town of Kulti Phase-II, West Bengal | ||||||||
2232 DUs BSUP for the town of Asansol Phase II . Barddhaman. West Bengal. | ||||||||
Rehabilitation of Slums in Asansol . Asansol Urban Area (through ADDA), West Bengal | ||||||||
Rehabilitation of Slums in Durgapur . Asansol Urban Area (West Bengal) | ||||||||
BSUP Scheme for the town of 4626 DUs BSUP Phase III for Asansol. Bardhaman. West Bengal | ||||||||
Rehabilitation of 2 Slums in Konnagar Municipality (Phase.I). Kolkata . West Bengal. | ||||||||
Rishra Housing Project in Rishra Municipal Area Phase.I (1 Slums) | ||||||||
Bally Housing Project in Bally Municipality (Phase.I). Kolkata . West Bengal | ||||||||
BSUP Scheme for Baruipur (Relocation). KMA. Kolkata. West Bengal | ||||||||
Rehabilitation of 1 Slums in Bidhannagar Municipality (Phase. I) .Kolkata. West Bengal | ||||||||
BSUP Scheme for the town of Baranagar ( Phase I) in . Kolkata Metropolitan Area | ||||||||
BSUP Scheme for the town of Budge Budge . West Bengal | ||||||||
416 DU`s Chetla Housing Project at Kolkata by KMDA, West Bengal | ||||||||
BSUP Scheme for the town of Baruipur. Kolkata region KMDA | ||||||||
Rehabilitation of 5 Slums in Baidyabati Municipality (Phase.I). Kolkata. West Bengal | ||||||||
240 DUs BSUP Scheme for the Town of Kanchrapara (Phase-2). North 24 Paraganas. West Bengal | ||||||||
Revised in BSUP Scheme for the town of Serampore Municipality (Phase.I) Kolkata . West Bengal. | ||||||||
Revised in BSUP Scheme for the town of South Dum Dum (Phase-I), West Bengal | ||||||||
364 Du For The Town of Konnagar (Phase Ii) Kolkata Ma | ||||||||
BSUP Scheme for the town of Pujali (Phase II)under kolkata region | ||||||||
500 Dus BSUP Scheme for the town of Bidhannagar Phase02 North 24 Paragans. West Bengal | ||||||||
BSUP Scheme for Bansberia. Kolkata region KMDA Phase II, West Bengal | ||||||||
Rehabilitation of 1 Slum In Champdany Municipality (Phase.I). Kolkata. West Bengal | ||||||||
Integrated Development of Slums in Barasat Municipality Area. Phase.I. Kolkata | ||||||||
Integrated Development of Slums in Barrackpore Municipality Area Phase I . (16 Slums) Kolkata | ||||||||
748 DU`s BSUP Scheme for the town of Dum Dum, Kolkata Region KMDA, West Bengal | ||||||||
G3 RCC Frame structure has been proposed for dwelling units with basic Infrastructure facilities Reconsideration of Housing for Urban Poor KMC. Kolkat | ||||||||
BSUP Scheme for the town of Khardah. West Bengal | ||||||||
Rehabilitation of 6 Slums in North Dum Dum.(Phase.I) kolkata, West Bengal | ||||||||
562 Dus Bsup For Titagarh Phase I. 24 Pargana (North) Kolkata Ma | ||||||||
Bsup Scheme For The Town of Pujali. West Bengal . | ||||||||
Rehabilitation of 13 Slums in Kalyani.(Phase.I). Kolkata | ||||||||
BSUP Scheme for rehabilitation of 6 Slums in the Town of Bhatpara Phase-I, North 24 Paraganas, West bengal | ||||||||
Integrated Development of Rehabilitation of 10 Slums in Kanchrapa (Phase-I) kolkata . West Bengal | ||||||||
Integrated Development of Slums in Rajarhat. Gopalpur Municipality Area . Phase.I (9 Slums). Kolkata | ||||||||
Improvement of Slum in Gayeshpur through KMDA. West Bengal | ||||||||
BSUP Scheme for Hooghly Chinsurah (Phase II)under kolkata region | ||||||||
Rehabilitation of 25 Slums in Uttarpara Kotrung Municipality (Phase.I) Kolkata.West Bengal | ||||||||
BSUP Scheme for the town Madhyamgram, Kolkata, West Bengal. | ||||||||
Integrated Development of Rehabilitation of 6 Slums in Kalyani (Phase.II) | ||||||||
500 Dwelling Units Bsup Scheme For The Town of Halisahar (Phase-2). North 24 Paraganas. West Bengal. | ||||||||
BSUP Scheme for 29 Slums in 3 clusters in the towns of North Barrackpore. Kolkata region KMDA | ||||||||
BSUP Scheme Scheme for the town of Bansberia . West Bengal | ||||||||
BSUP Scheme for the town of Hooghly Chinsurah .West Bengal | ||||||||
Revised of BSUP Scheme for construction of 1177 DU`s in the town of Chandernagore Phase-III, Distt. Hooghly, West Bengal. | ||||||||
BSUP Scheme for the town of Kamarhati . Kolkata. West Bengal. | ||||||||
1108 Dus BSUP Scheme for the town of Bally Phase-2. Kolkata Metropolitan Area. Howrah West Bengal | ||||||||
1120 DUs for Garulia (Kolkata MA), West Bengal | ||||||||
BSUP Scheme for Budge Budge Ph-II. Distt. 24 Parganas ( South). Kolkata Metropolitan Area. West Bengal | ||||||||
BSUP Scheme for the town of Khardah Phase II, West Bengal | ||||||||
BSUP Scheme for the town of Barrackpore (Phase II) under Kolkata region, West Bengal | ||||||||
BSUP Scheme for the town of Panihati (Phase II) under Kolkata region, West Bengal | ||||||||
Revised of BSUP Scheme for construction of 1905 DU`s in the town of Chandernagore Phase-I, Distt. Hooghly, West Bengal | ||||||||
BSUP Scheme for the town of Madhyamgram Phase II in . Kolkata Metropolitan Area | ||||||||
BSUP Scheme for the town of Rishra (Phase II) under kolkata region, West Bengal | ||||||||
Nonadanga Housing Project (Kmda) Kolkata Metropolitan Development Authority. | ||||||||
Integrated Development of Slums in Uluberia Municipality Area (Phase.I) (7 Slums) . Kolakata . West Bengal. | ||||||||
899 DUs Detailed Project Report for "Basic Services to the Urban Poor under BSUP. JNNURM in 17 Slums for Titagarh Municipal Area. Kolkata. West Bengal | ||||||||
BSUP Scheme for the town of Rajpur Sonarpur (Phase II)under kolkata region | ||||||||
BSUP Scheme for the Town of Panihati. Kolkata Metropolitan Development Area . West Bengal | ||||||||
BSUP Scheme for the town of Serampore (Phase II) under kolkata region | ||||||||
Rehabilitation of 15 Slums in Rajpur Sonarpur (Phase-1) : Kolkata, West Bengal | ||||||||
1197 DUs BSUP Scheme for the Town of Konnagar (Phase-3). Hooghly. West Bengal | ||||||||
BSUP Scheme for the town of Naihati in . Kolkata Metropolitan Area | ||||||||
BSUP Scheme for the town of Uluberia (Phase II)under kolkata region | ||||||||
Slum Development Programe in Barrackpore. KMDA. West bengal | ||||||||
Revised in Sanctioned DPR - BSUP Scheme for Baruipur (Ph-II). KMA. Kolkata. West Bengal | ||||||||
Integrated Housing and slum Development Project for Anandnagar (ward 59). Jalpara (ward 58) Garden Reach I. (ward 138) under BSUP in Kolkata | ||||||||
BSUP Scheme for the town of Maheshtala (Phase II), West Bengal | ||||||||
Curtailment of BSUP Scheme for the town of Halisahar Ph-I, 24 Paraganas (North), West Bengal. | ||||||||
BSUP Scheme for Rajarhat0 Gopalpur (Ph0II). KMA. Kolkata. West Bengal | ||||||||
BSUP Scheme for North Dum Dum (Ph-II) . KMA. Kolkata . West Bengal | ||||||||
BSUP Scheme for the town of Barasat (Phase II) under kolkata region | ||||||||
BSUP Scheme for the town of Bhadreswar Municipalty. Kolkata West Bengal. | ||||||||
Revised BSUP Scheme for the town of Maheshtala (Phase.I). South 24 Paraganas, West Bengal | ||||||||
Integrated Development of Slums in Howrah Municipal Corporation .Phase I ( Slum) | ||||||||
Revised of BSUP Scheme for construction of 2092 DU`s in the town of Champdani Phase-II, Distt. Hooghly, West Bengal (KMDA) | ||||||||
1947 DUs BSUP Scheme for the Town of Bhatpara (Ph-2). North 24 Paraganas. West Bengal | ||||||||
BSUP Scheme for the town of Gayeshpur (Phase II) under Kolkata region, West Bengal | ||||||||
1469 DUs BSUP Scheme for the Town of Rajarhat Gopalpur (Phase IV). North 24 Parganas. West Bengal | ||||||||
1406 Units Detailed Project Report for "BSUP Scheme for the town of Madhyamgram (Phase-III). West Bengal | ||||||||
1499 DUs BSUP Scheme for the Town of Dankuni (Phase-1). Hooghly. West Bengal | ||||||||
1573 DUs BSUP Scheme for the Town of Rajarhat Gopalpur (Phase- III). North 24 Paraganas. West Bengal | ||||||||
1598 DUs BSUP Scheme for the Town of Serampore (Phase 3). Hoogly. West Bengal | ||||||||
BSUP Scheme for the town of Kalyani (Phase-III) under Kolkata region, West Bengal | ||||||||
2000 DUs Integrated Development of Slums under BSUP Scheme of JNNURM for the Town of North Dum Dum (Phase-3). 24 Paraganas (North). West Bengal | ||||||||
Integrated Housing Project for Slum Dwellers of Rajarghat. kachharipara and Hatgachia area at Mouza Boinchtala in Kolkata (KMC) | ||||||||
Rehabilitation of Kumartuli Slums In Kolkata. West Bengal (Additional Project) | ||||||||
200 Transit DUs Rehabilitation Project of Kumartli for the artisans of Kumartuli under BSUP Scheme of JNNURM at Rabindra Sarani. Kolkata by KMDA. (Additional Project) | ||||||||
Revised in Sanctioned Scheme- BSUP Scheme for the Town of Baranagar (Phase-II), 24 Paragans (North), West Bengal. | ||||||||
BSUP Scheme for the town of Halisahar, Phase-III, 24 Paraganas (North) West Bengal | ||||||||
BSUP Scheme for the town of Maheshtala, Phase-III 24 paraganas (South), West Bengal | ||||||||
500 DU`s Detailed Project report for "BSUP Project for Canal South road.", West Bengal | ||||||||
16 DU`s Detailed Project report for "BSUP Project for Chetla Haat." West Bengal | ||||||||
36 DU`s Detailed Project report for "BSUP Project for Sen Pally (Sardar Bustee), West Bengal | ||||||||
Revised BSUP Project for Maheshtala Municipality (Phase-IV) for 1184 Dus, Kolkata, West Bengal | ||||||||
BSUP Project for construction of 1034 Dus (in-situ) in 8 Slums of Bhatpara Municipality (Phase-III) | ||||||||
Revised BSUP Phase-IV for construction of 154 DU`s in three Slums of Chandernagore Municipality, West Bengal | ||||||||
BSUP Project for construction of 799 Dus (in-situ) in 5 slum of Bhatpara Municipality (Phase-IV) | ||||||||
BSUP Project for construction of 1031 Dus (in-situ) in 7 Slums of Kanchrapara Muncipality (Phase-III) | ||||||||
BSUP Scheme for the town of Ultadanga, under Kolkata improvement construct for 1000 DU`s, West Bengal. | ||||||||