Selected State/Project/Agency-wise Status of Ongoing Hydro Power Projects (Excluding Renewable and Project 25MW Capacity) in India (2007-2012) | |||||
Project/Capacity/Agency/ State Date of Appproval | Commissioning Schedule | Delays Relating to Latest V/S Last Approved/Original | Project Expenditure (Rs. in Crore) | Reasons for Time and Cost Over Run | |
Original mm/yy | Latest mm/yy | ||||
Himachal Pradesh | |||||
Chamera-III (3x77 MW) NHPC Himachal Pradesh 01.09.2005 | |||||
Parbati-III (4x130 MW) NHPC Himachal Pradesh 09.11.2005 | |||||
Budhil (2x35MW) Himachal Pradesh M/s. Lanco Green Power Pvt. Ltd. NA 02.06.06 | |||||
Jammu and Kashmir | |||||
Uri-II (4x60 MW) NHPC Jammu and Kashmir 01.09.2005 | |||||
Chutak (4x11 MW) NHPC Jammu and Kashmir 24.08.2006 | |||||
Nimoo Bazgo (3x15 MW) NHPC Jammu and Kashmir 24.08.2006 | |||||
Uttarakhand | |||||
Koteshwar (4x100 MW) THDC, Uttarakhand 10.4.2000 | |||||
Madhya Pradesh | |||||
Maheshwar (10x40 MW) SMHPC M.P. 30.12.96 | |||||
Andhra Pradesh | |||||
Nagarjuna Sagar Tail Pool Dam (2x25 MW) APGENCO 17.01.2005 | |||||
Kerala | |||||
Tamil Nadu | |||||
BhavaniKattalai H.E. Project Barrage II (2x15 MW) TNEB 11.06.99 | |||||
BhavaniKattalai H.E. Project Barrage III (2x15 MW) TNEB 27.03.02 | |||||
West Bengal | |||||
Teesta Low Dam-III (4x33 MW) NHPC West Bengal 30.10.2003 | |||||
Teesta Low Dam IV (4x40 MW) NHPC WB 30.09.2005 | |||||
Meghalaya | |||||
Myntdu (2x42MW+(1x42 MW) MeSEB 09.06.2003 | |||||
Sikkim | |||||
Teesta Stage III (6X200 MW) Sikkim M/s TeestaUrja Limited 12.05.2006 (TEC) | |||||
Chujachen (2x49.5 MW) Sikkim M/s. Gati Infrastructure Ltd. 30.11.04 |