Status of Central Sector Projects Showing Cost Overruns in India (As on 01.03.2016) | ||||||||
Projects | Sectors | Implementing Agency | Date of Approval (Month/Year) | Original Date of Commissioning (Month/Year) | Anticipated Date of Commissioning (Month/Year) | Original Cost (Rs. in Crore) | Cost Anticipated (Rs. in Crore) | Cost Overrun^ (%) |
Prototype Fast Breeder Reactor (Bhavini, 500 Mwe) | ||||||||
Kudankulam App (Npcil) | ||||||||
Supply of 56 Nos Airfield Fire Tenders At Various Airports | ||||||||
Nigahi Oc Expansion Project 10 Mty to 15 Mty, Singrauli | ||||||||
Adriyala Shaft Project | ||||||||
Ramagundam Oc-Ii Extension | ||||||||
Rfr of Manuguru Oc Project | ||||||||
New Sewage Treatment Plant Package, Rcf Trombay | ||||||||
National Automotive Testing and Rd Infrastructure Project (Natrip) | ||||||||
Assam Gas Cracker Project | ||||||||
Integrated Refinery Expansion Project | ||||||||
Mangalore Hassan Mysore Solur Lpg Pipeline (Mhmslpl) | ||||||||
Uran Chakan/Shikrapur Lpg Pipeline | ||||||||
50 Mw Capacity Wind Power Project Under Phase Ii | ||||||||
Paradip Refinery Project | ||||||||
Lpg Terminal At Kochi | ||||||||
Marketing Top At Korba | ||||||||
Strategic Crude Oil Storage Project At Padur | ||||||||
Strategic Crude Oil Storage Project At Mangalore | ||||||||
Upgradation of Crude Oil Pump Stations of Naharkatiya-Barauni Crude Oil Trunk Pipeline | ||||||||
Secondary Tank Farm With Dehydration Facility and Effluent Treatment Plant At Madhuban | ||||||||
Integrated Development of B-127 Fields | ||||||||
Conversion of Rig Sagar Samrat to Mobile offshore Production Unit(Mops) | ||||||||
Gamji Redevelopment Project | ||||||||
Mh North Redevelopment Phase Iii | ||||||||
Raghunathpur Thermal Power Station Phase-I | ||||||||
Bokaro Thermal Power Station-A | ||||||||
Kameng Hydroelectric Project (Neepco) | ||||||||
Tuirial Hydro Electric Project (60Mw) | ||||||||
Pare Hydro Electric Project | ||||||||
Tripura Gas Based Power Project | ||||||||
Subansiri Lower H.E.P (8X250 Mw) (Nhpc) | ||||||||
Parbati Hep (4X200 Mw) (Nhpc) Ii | ||||||||
Kishanganga Hep (3X110 Mw) | ||||||||
Teesta Low Dam Hep, Stage-Iv (4X40 Mw) (Nhpc) | ||||||||
Barh Stpp(3X660Mw) Ntpc | ||||||||
Bongaigaon Thermal Power Project | ||||||||
Tapovan-Vishnugad Hep (4X130Mw) | ||||||||
North- East North Western Interconnector I Project | ||||||||
Transmission System Associated With Pallatana Gbpp and Bpts. | ||||||||
System Strengthening in North/West Part of Wr For Ipp Projects in Chattisgarh | ||||||||
Kunadankulam App Trans System (Pgcil) | ||||||||
Western Region Strengthening Scheme-V | ||||||||
Sytem Strengthening Xiii of Sr Grid | ||||||||
Transmission System For Connectivity of Essar Power Gujarat Limited | ||||||||
Sytem Strengthening of Southern Region - Xiv | ||||||||
Tehri Pumped Storage Plant(1000Mw) | ||||||||
Ahmednagar-Parli Vaijnath(Nl) Cr | ||||||||
Wardha-Nanded Maharashtra | ||||||||
Panvel Pen Doubling | ||||||||
Pen Roha Doubling | ||||||||
Amravati-Narkher Nl(Cr) | ||||||||
Kalyan-Kasara 3Rd Line | ||||||||
Khurda Road-Bolangir(Nl)Ecor | ||||||||
Sambalpur-Talcher Doubling | ||||||||
Kirandul - Jagdalpur Doubling | ||||||||
Sakri-Hasanpur Road (Nl) | ||||||||
Chhapra-Muzaffarpur (Nl) | ||||||||
Delang-Puri Doubling | ||||||||
Jharsuguda-Rengali Doubling | ||||||||
Talcher-Bimalagarh(Nl)(Ecor) | ||||||||
Patna Ganga Bridge (Nl), Ecr | ||||||||
Rail-Cum-Road Bridge At Munger (Nl), Ecr# | ||||||||
Motihari-Sitamarhi (Nl) | ||||||||
Jayanagar-Darbhanga-Narkatia Ganj(Gc),Ecr | ||||||||
Khagaria-Kusheshwar Asthan (Nl) (Ecr) | ||||||||
Hajipur-Ramdayalunagar Doubling | ||||||||
Mansi-Purnia (Extension of Mansi-Saharsa) Gan Ecr | ||||||||
Kosi Bridge (Nl), Ecr | ||||||||
Mumbai Urban Transport Project Phase-Ii | ||||||||
Tollyganj-Garia With Extension to Dum Dum-Noapara and Noapara-Nscb Airport(Mtp) | ||||||||
Belapur-Seawood-Uran Electrified Double Line(Mtp) | ||||||||
Multi Modal Transport System(Mmts) Phase-Ii Hyderabad | ||||||||
Gwalior-Seopurkala With Extension to Kota (Gc) | ||||||||
Dholpur-Sirmuttra With Extension to Gangapurcity and Mohari-Tantpur & Tanpur-Bansi Paharpur | ||||||||
Guna-Etawah Via Shivpuri-Gwalior -Bhind Nl, (Ncr) | ||||||||
Agra-Etawah Via Fatehabad and Bah (Nl) Ncr | ||||||||
Etawah-Mainpuri (Nl),Ncr | ||||||||
Kanpur Kasganj Mathura(Gc) Ner | ||||||||
Chhapra-Ballia Up | ||||||||
Maharajganj-Masrakh (Nl) - Ner | ||||||||
Ghazipur - Aunrihar (40 Km) | ||||||||
Jiribam to Imphal (Tupui)(Nl)(Nefr) | ||||||||
Lumding-Silchar Jiribam, Badarpur-Baraigram Kumarghat National Project# | ||||||||
Bputra Bridge At Bogibil and Link Lines Nefr# | ||||||||
Sevok Rangpo, Nefr | ||||||||
Bhairabi Sairong, Nl, Nefr | ||||||||
New Line From Dimapur to Zubza(Kohima) National Project (Nefr) | ||||||||
Agartala Sabroom, Nl, Nefr | ||||||||
New Maynaguri to Jogighopa Via Changrabandha (Nl),Nefr | ||||||||
New Bg Rly Line From Eklakhi-Balurghat Including Gazole-Itahar(Nl),Nefr | ||||||||
Katihar - Jogbani (Gc)(Nefr) | ||||||||
New Bg Line From Byrnihat to Shillong | ||||||||
New Jalpaiguri-Siliguri-New Bongaigaon Including Br. Line and Mm For Chalsa-Naxal& Rajabhatkhowa-Jai | ||||||||
Agartala-Akhaura Nl | ||||||||
New B.G. Line From Araria to Galgalia (Thakurgung), Nefr | ||||||||
New Bg Line From Balurghat to Hilly Nfr | ||||||||
Construction of Nl From Kumarghat-Agartala# | ||||||||
New Bg Line From Kaliyaganj to Buniadpur | ||||||||
Aluabari Road Siliguri Junction Via Galgalia, Nefr | ||||||||
New B.G. Line From Tetelia to Byrnihat (National Project), Nefr | ||||||||
Kishanganj Jalalgarh, Nl, Nefr | ||||||||
Murkongselek-Pasighat Nl | ||||||||
New Coochbehar to Samuktala | ||||||||
Dimapur-Tizit Nl | ||||||||
New Bg Line From Jagbani to Biratnagar | ||||||||
Ambari Falakata to New Maynaguri | ||||||||
Lumding-Hojai Patch Doubling Project | ||||||||
Katakhal to Bhairabi | ||||||||
New Bongaigaon-Rangia-Kamakghya Doubling | ||||||||
New Coochbehar-Gumanihat Patch Doubling Project | ||||||||
Udhampur-Srinagar-Baramulla (Nl),Nr | ||||||||
Utratia-Zafrabad, Nr (Line Doubling)# | ||||||||
Bhanupali-Bilaspur Beri Nl | ||||||||
Nangaldam-Talwara(Nl),Nr | ||||||||
Jind-Sonepat (Nl),Nr | ||||||||
Rohtak-Meham Hansi | ||||||||
Jalandhar-Pathankot-Jammu-Tawi (Ld),Nr | ||||||||
Haridwar-Laksar | ||||||||
Ratlam-Dungarpur Via Banswara (Nl) | ||||||||
Mavli Junction-Bari Sadri, Mm of Ajmer- Chittsurgarh-Udaipur | ||||||||
Ratangarh-Sardarsahar (Mm of Sadulpur-Bikaner and Ratangarh-Degana Gc) | ||||||||
Thiyat Hamira-Sanu | ||||||||
Ajmer-Bangurgram | ||||||||
Jaipur - Ringus - Churu and Sikar - Loharu Guage Conversion (Nwr) | ||||||||
Electrification of Khurja-Meerut-Saharanpur and G`Bad-Meerut | ||||||||
Sukinda Road - Angul (Nl)(Ecor) | ||||||||
Haridaspur-Paradeep(Nl) | ||||||||
Dalli-Rajhara - Raoghat(Part of Dalli-Rajhara-Jagdalpur),Nl,Rvnl | ||||||||
Bhopal Bina 3D Line Doubling | ||||||||
Raichur-Guntakal(Dl)(Scr) | ||||||||
Khurda Road - Barang 3Rd Line (Dl) (Ecor) | ||||||||
Rajatgarh-Barang(Ld),Ecor | ||||||||
Cuttack - Barang (Ld) | ||||||||
Salka Road -Anupnagar Line Doubling | ||||||||
Akola-Khandwa Gc Akola-Akot | ||||||||
Kazipet-Vijayawada 3Rd Line With Electrification | ||||||||
Pedapalli-Karimnagar-Nizamabad Nl(Scr) | ||||||||
Nandyal-Yerraguntla(Nl),Scr | ||||||||
Kotlpalli-Narasapur (Nl) (Scr) | ||||||||
Gulbarga-Bidar,Scr(Nl) | ||||||||
Muneerabad-Mahaboobnagar(Nl),Scr | ||||||||
Manoharabad-Kothpall New Line(Scr) | ||||||||
Macherla-Nalgonda(Nl)(Scr) | ||||||||
Gadwal - Raichur (Nl), Scr | ||||||||
Bhadrachalam Road-Sattupalli | ||||||||
Gondia-Jabalpur(Gc),(Secr) | ||||||||
Chhindwara - Nagpur (Gc)(Secr) | ||||||||
Bankura - Damodar (Gc) (Ser) | ||||||||
Tamluk Digha,Line Doubling (Ser) | ||||||||
Howrah-Amta-Champadanga Nl (Ser) | ||||||||
Bhadutola-Jhargram Via Lalgarh (Nl) | ||||||||
Digha-Jaleswar Including Mm For Digha-Egra | ||||||||
Mm From Buramara-Chakulia | ||||||||
Dangoaposi-Rajkharswan 3Rd Line Doubling | ||||||||
Bowaichandi-Arambagh | ||||||||
Mm From Panskura-Ghatal Nl | ||||||||
Ranchi-Lohardaga(Gc),Ser | ||||||||
Manoharpur-Bondamunda 3Rd Line Doubling | ||||||||
Goelkera-Manoharpur,(Ld)(Ser) | ||||||||
Champajharan-Bimalgarh Doubling Extension | ||||||||
Rajkharswan- Chakradharpur 3Rd Line (20 Km) Jharkhand | ||||||||
Angamali-Sabarimala (N.L.)(Sr) | ||||||||
Mayladuthurai-Thiruvarur-Karaikudi-Thiru `Pondi-Agastiyampalli | ||||||||
Tiruchirappali-Nagore-Karaikkal(Sr)(Gc) | ||||||||
Quilon-Tirunelveli-Tenkasi-Virudhunagar(Sr)(Gc) | ||||||||
Chengalpattu-Villupuram Doubling With New Mm For Tambaram-Chengalpattu 3Rd Line Gc Alonwith Electrif | ||||||||
Chennai-Cuddalore Via Mamallapuram | ||||||||
Sriperumbudur-Guduvanchery With Spur to Irungattukkottai-Avadi-Sriperumbudur | ||||||||
Karur-Salem(Nl),Sr | ||||||||
Tidivanam-Nagari (Nl) | ||||||||
Dindigul-Pollachi-Palghat-Pollachi and Coimbatore | ||||||||
Quilon-Tirunelveli - Trichendur, Tenkasi | ||||||||
Villupuram-Dindigul With Electrification | ||||||||
Tindivanam-Gingee-Tiruvannamalai (Nl) | ||||||||
Cuddalore-Salem Via Vriddhachalam Gc | ||||||||
Calicut-Mangalore (Dl) (Sr) | ||||||||
Erode-Palani | ||||||||
Madurai-Bodinayakkanur | ||||||||
Chennai Beach-Tambaram-Chengalpattu Suburban Gc | ||||||||
Madurai-Tuticorin Via Aruppukkottai | ||||||||
Attippattu-Puttur | ||||||||
Kuruppanthara-Chingavanam | ||||||||
Chengannur-Chingavanam | ||||||||
Hubli-Ankola(Nl),Swr | ||||||||
Banglore - Satyamangalam (Nl)(Swr) | ||||||||
Munirabad (Gingera) -Raichur Nl | ||||||||
Hassan-Bangalore Via Shravana-Belgola(Nl),Swr | ||||||||
Tumkur-Chitradurga-Davengere Nl | ||||||||
Gadag-Wadi Nl | ||||||||
Rayadurga-Tumkur Nl | ||||||||
Bagalkot-Kudachi Nl | ||||||||
Ramanagram-Mysore Doubling With Electrification of Kengesii- Musore (Swr) | ||||||||
Shimoga-Harihar Nl | ||||||||
Srinivasa-Pura-Madanapalli Nl | ||||||||
Chikballa-Pur-Putttaparthy-Sri Satya Sai Nilayam Nl | ||||||||
Chikballa-Pur-Gowribidanur Nl | ||||||||
Toranagallu-Ranjitpura Dl | ||||||||
White Field-Kolar Nl | ||||||||
Lalitpur-Satna-Rewa-Singruli Nl, (Ncr) | ||||||||
Ramganjmundi-Bhopal (Nl),Wcr | ||||||||
Gonda Gorakhpur Loop With Anand Nagar Nautanwa Gc (260 Km) | ||||||||
Ratlam-Mhow-Khandwa-Akola (Gc) | ||||||||
Rajkot-Veraval,Wansjalia to Jatalsar With New Mm For Shapur-Saradiya and Somnath-Kodinar (Gc) | ||||||||
Viramgam-Bhildi(Wr),Gc | ||||||||
Viramgam-Samakhiali (Dl) | ||||||||
Bhavnagar-Workshop Facilities For 50 Bg Coaches Poh Per Month (Wr) | ||||||||
Bhuj-Naliya(Gc) With Extension From Naliya to Vayor (Wr) | ||||||||
Construction of Paved Shoulders in Km.81/0 to 203/0 Including Reconstruction and Widening of Culvert | ||||||||
Rehabilitation and Upgradation of Nh 226 E From 0-1 - 66-20 to 2 Lane With Paved Shoulders on Epc Mo | ||||||||
Panipat-Jalandhar 6 Lane(Km 96 to 387.1 Km) | ||||||||
Maibang to Lumding (As-25), Km.83.400 to Km.111.000 | ||||||||
Harangajo to Maibang, Nh-54 | ||||||||
Maibang to Lumding (As-24), Km.111.000 to Km.126.450 | ||||||||
Brahmputra Bridge,Nh No-31 | ||||||||
Harangajo to Maibang (As-23), Km.126.450 to Km.140.700 | ||||||||
Ganga Bridge to Ramdevi Crossing Ph.Ii Nh-25, Km.75-80.06 | ||||||||
Chambal Bridge, Nh-76 (Rj-5) | ||||||||
Construction of Godavari River Bridge Near Venkatpuram Including Approach Road on Nh-202 Under Lwe S | ||||||||
Two Laning of Khonsa - Tissa - Longding (Nh-52B) (42.50 Km) in Arunachal Pradesh Under Arunachal Pra | ||||||||
Two Laning of Yupia - Hoj Section (20.40 Km) in Arunachal Pradesh Under Arunachal Pradesh Package of | ||||||||
Construction of 6.80 Km 2 Lane With Paved Shoulders Alappuzha Bypass on Nh47 New Nh 66 From Km 408.1 | ||||||||
Construction of 13.0 Km 2 Lane With Paved Shoulders Kollam Bypass on Nh47 (New Nh 66) From Km 486/50 | ||||||||
Rehabilitation and Upgradation of Nh-67 From Km 695.000 to Km 741.950 (Atmakur Nellore Section) In | ||||||||
4 Laining With Paved Shoulders of Dogal Kalan to Punjab/Haryana Border Sec.Of Nh-71(New Nh-52) From | ||||||||
Rehabilitation and Upgradation of Nh-221 From Km 121/0 to 165/00 (Of Vijayawada-Jagdalpur Rudrampur | ||||||||
Construction of Coal Berth-4 At Kamarajar Port Limited | ||||||||
Construction of offshore Container Berths and Development of Container Terminal on Bot Basis in Mumb | ||||||||
Ennore Manali Express Way,F/O Special Purpose Vehicle (Spv) | ||||||||
Rail Connectivity to Ictt At Vallarpadam At Cochin Port Trust | ||||||||
Construction of Medical College and Hospital At Gulbarga | ||||||||
Construction and Mainteinance of Rural Road Under Pmgsy Phase Viii | ||||||||
Construction and Mainteinance of Rural Road Under Pmgsy Phase V | ||||||||
Construction and Mainteinance of Rural Road Under Pmgsy Phase Vi | ||||||||
Construction of Paramedical and Allied Health Institute At Gulbarga | ||||||||
Revamping of Sinter Machines - 1 and 2 | ||||||||
Residential and Other Complexes For The Campus of Iit Patna At Bihta | ||||||||
Bangalore Metro Rail Project |